- DOM/1, cl 24
- JCT81, supplemental cl 1
- ICE 6th edition, cl 66
- Engineering and Construction Contract,(10) cl 9
- GC/Works/1, cl 59
- IChemE Lump Sum Contract, cl 46
- FIDIC Design and Build, cl 20.4
Meet the eight points:
|
DOM/1, cl 24 |
JCT81, S1 |
ICE 6th edn,
cl 66 |
ECC (NEC),
cl 9 |
GC/
Works/1,
cl 59 |
IChemE Lump Sum, cl 46 |
FIDIC
D and B, cl 20.4 |
1 - Notice any time |
No |
No |
Maybe |
No |
No |
No |
Yes |
2 - Referral in 7 days |
No |
No |
No |
No |
No |
No |
Maybe |
3 - 28 days for decision |
No |
No |
No |
No |
Yes |
No |
No |
4 - 14 days extension |
No |
No |
No |
No |
No |
No |
No |
5 - Impartiality |
? |
? |
? |
? |
? |
? |
Yes |
6 - Initiative |
No |
No |
No |
No |
No |
No |
Yes |
7 - Binding pro tem |
Yes |
Yes |
No |
No |
Probably not |
No |
Yes |
8 - Immunity |
No |
No |
Yes |
Probably not |
No |
No |
Yes |
Although the producers of these forms are making amendments
designed to make them compliant, it is likely that it will be some time
before the old forms are fully out of circulation.
What is Adjudication?
Adjudication is not the invention of the construction
industry. Adjudication is provided for by statute in a number of areas,
eg the Asylum and Immigration Appeals Act 1993, the Social Security
Act and the Prison Rules. It is a technique that is used in other non-statutory
contexts, for example the Law Society Compensation fund.(11)
The common feature of these adjudication processes is that they all
endeavour, in one way or another, to resolve some sort of dispute or
question by means of something other than litigation or arbitration.(12)
Comparison with Arbitration, Certification, Mediation
and other Consensual Processes
The dividing line between the three main types of third
party decision-making process, namely
- arbitration
- expert determination, and
- adjudication(13)
is not always distinct.
Arbitration or adjudication?
There are statutory definitions of arbitration:
Arbitration Act 1950 Section 32
In this part of this Act, unless
the context otherwise requires, the expression "Arbitration Agreement"
means a written agreement to submit present or future differences
to arbitration, whether an Arbitrator is named therein or not
Arbitration Act 1996 Section 6(1)
In this Part an "Arbitration Agreement"
means an agreement to submit to arbitration present or future disputes
(whether they are contractual or not).
It is, however, clear that the label used by the parties
themselves is not conclusive. The issue has arisen in the context of
rent review arrangements, where provisions in leases sometimes provide
for arbitration and sometimes for expert determination. In Langham
House Developments Limited v Brompton Securities Limited,(14)
the court said:
Where a third party is to determine
the rent under the provisions of a rent review clause, the third party
may act either as an expert or an arbitrator: normally the clause
will make it clear in what capacity the third party is to act; if
it does not, it will be a matter of construction as to which was intended
and the mere description of a third party as 'expert' or 'arbitrator'
in the lease will not necessarily be conclusive.
|
9. Difficult questions may
arise where the parties have agreed a non-compliant adjudication procedure,
which is likely to conflict with the statutory scheme.
10. The contract previously known as the New
Engineering Contract.
11. The courts sometimes also talk of 'adjudication'
by courts and arbitrators, but this use of the word is not of interest
in this context.
12. The law has traditionally treated litigation
and arbitration as being essentially similar in nature. For example,
in Northern Regional Health Authority v Derek Crouch Construction
Limited [1984] QB 644 at 670, Sir John Donaldson said 'Arbitration
is usually no more and no less than litigation in the private sector.
The Arbitrator is called upon to find the facts, apply the law and grant
relief to one or other or both of the parties'. The passing of the Arbitration
Act 1996 may lead to some change in this attitude.
13. In this chapter, the various forms of
dispute resolution board arrangements that have grown in popularity
in recent years, particularly in international contracts, are treated
as a subset of adjudication.
14. (1980) 265 Estates Gazette 919.
|
In A Cameron v John Mowlem & Co
the question arose as to whether the decision of an adjudicator
could be enforced as an arbitrator's award. At first instance,(15)
Judge Esyr Lewis QC held that a decision of an adjudicator under a JCT
contract is not so enforceable, his reasoning being that 'The Adjudicator
... does not perform an arbitral function and does not make any final
award definitive of the parties rights'.
That decision was upheld on appeal,(16) the
Court of Appeal saying:
Mr Richard Fernyhough QC for Cameron
argued in this Court that the judge was wrong and that the adjudication
process qualified as an arbitration. He referred to the list of factors
in Mustill and Boyd, Commercial Arbitration (2nd edn, 1989)
pp 41 et seq which may be material in determining whether a procedure
qualifies as an arbitration. Undoubtedly some at least of those factors
are present in the adjudication process but rather than proceeding
by reference to a list we prefer to focus upon the subcontract. That
does contain an undoubted arbitration provision (Article 3) and it
is by an arbitrator appointed under that Article that a dispute as
to set-off is to be ultimately resolved whatever an Adjudicator may
decide (see clauses 24.1.1 and 24.3.1). An Adjudicator's decision
is 'binding ... until' determination by an Arbitrator. The decision
has an ephemeral and subordinate character which in our view make
it impossible for the decision to be described as an award on an arbitration
agreement. The structure of the subcontract is against that conclusion.
We would dismiss this appea".
Conversely, in Drake & Scull Engineering Limited
v McLaughlin & Harvey Plc,(17) the court found that
the same adjudication procedure was part of the arbitration procedure,
saying:
This action is not brought to go outside the agreed
arbitration machinery, but to enforce the agreed arbitration machinery
... the Plaintiffs are coming to court to enforce an order made by
an adjudicator in the course of the arbitration procedure.
Similarly, in Cape Durasteel Limited v Rosser &
Russell Building Services Limited,(18) Judge Humphrey
Lloyd QC, Official Referee, found that the following provision namely:
In the event of any dispute arising
out of or in connection with the subcontract the parties agree to
refer such dispute to adjudication to a person agreed upon or failing
agreement to some person appointed by the President for the time being
of the Chartered Institute of Building Services Engineers.
did constitute an arbitration agreement.
In the Channel Tunnel case, disputes arose out of the
'lump sum works', ie the design and construction of the terminals at
each end of the Channel Tunnel and the design, supply, installation
and commissioning of fixed equipment. The adjudication provision(19)
contained the following features:
- disputes in the first instance went to a panel of three persons,
who were expressed to be 'acting as independent experts but not as
arbitrators'
- the unanimous decision of the panel was final and binding unless
challenged in subsequent arbitration.
Disputes arose; the contractors threatened to stop work
on the cooling system. The employer sought an injunction restraining
the contractors from taking that course.
The court declined to grant that injunction, largely
on the basis that it should not interfere with the dispute resolution
mechanism that the parties had chosen for themselves. The Court of Appeal
said:
It has not been suggested
that this paragraph provides in law for an arbitration despite the
term that the panel members shall act as experts and not as arbitrators.
So we need express no opinion on that point.(20)
The Court of Appeal may or may not have been offering
a hint here that they would have entertained an argument, if advanced,
that the Panel was in fact acting in an arbitral capacity, as opposed
to a mere expert capacity. In any event, it was conceded when the matter
went on to the House of Lords(21) that the panel procedure
did not amount to part of the arbitral process, and so the point was
not taken further.(22)
If any procedure, whatever its label, is found to be
an arbitration procedure, then the result is that the provisions of
the Arbitration Acts will apply;
Decisions and appeals
It is generally(23) agreed that adjudication
should be final and binding only pro tem, subject to review.
Dependent upon the way the adjudication procedure is worded, the review
may be in either of two forms:
(1) A review de novo, such that a court or
arbitrator is free to consider the dispute from scratch, without
troubling itself as to what the adjudicator decided and why.
(2) Alternatively, the subsequent court or arbitration
proceedings may be limited to points of challenge, whereby the court
or arbitrator is stuck with the adjudicator's decision unless and
to the extent that it can be shown that the adjudicator was wrong
in his decision. Such a position is very much akin to the powers
of the court to review certificates as explained in Balfour Beatty
v Docklands Light Railway,(24) and at least one Official
Referee, Judge Anthony Thornton, has in the past expressed the view
that that is all an arbitrator is entitled to do in relation to
a certificate.
Natural Justice
The High Court does, of course, exercise very considerable
control both over the proceedings of inferior courts and over the proceedings
of arbitrators; in practice, that control has exercised a very significant
influence. Arbitrators are not infrequently persuaded into aping High
Court procedure in every respect.
The control exercised by the courts over adjudication
is rather less tight, but in practice can remain a significant influence.
A distinction needs to be drawn between public matters and private matters.
(1) Public matters
Where the adjudication amounts to some sort of quasi-judicial
process, then the courts can and frequently do intervene by way of judicial
review.(25) In particular, the court may intervene where
the challenge is made, not upon the rightness or otherwise of the decision,
but upon the ground that the practice or procedure of the adjudication
process has contravened the principles of 'natural justice'.
The principles of natural justice are plainly less demanding
than those required of a court or an arbitrator, and there is no hard
and fast definition of the requirements. In Russell v Duke of Norfolk,(26)
the Court of Appeal said:
There are, in my view, no words
which are of universal application to every kind of enquiry and every
kind of domestic tribunal. The requirements of natural justice must
depend on the circumstances of the case, the nature of the enquiry,
the rules under which the tribunal is acting, the subject matter that
is being dealt with, and so forth; accordingly, I do not derive much
assistance from the definitions of natural justice which have been
from time to time used, but, whatever standard is adopted, one essential
is that the person concerned should have a reasonable opportunity
of presenting his case.
In Wiseman v Borneman,(27) the House
of Lords said:
Natural justice requires that the
procedure before any tribunal which is acting judicially shall be
fair in all the circumstances, and I would be sorry to see this fundamental
principle degenerate into hard-and-fast rules.
In various contexts, the courts have found that it is
a requirement of justice that a person should not be judge in his own
cause, that everyone is entitled to a fair hearing and, depending on
the circumstances, that the parties are entitled to reasons for the
decision. In other circumstances, the courts have found that it is not
necessarily a requirement that they are entitled to legal assistance,
or to prior notice of the subject matter of the process.
(2) Private matters
The cases on natural justice often involve complaint
about the way some agency of the Government has exercised its executive
powers, but this is not always so. For example, in R v Lord President
of the Privy Council, ex p Page,(28) a dispute arose
between a university and a university lecturer. The lecturer was made
redundant, and took the matter to the visitor of the university (a procedure
very similar to an adjudication process under a building contract save
that the lecturer's rights were governed, not merely by a private contract,
but by the statutes of the university that had been made under a Royal
Charter).(29) The eventual decision of the House of Lords
was that the visitor's decision was subject to judicial review, but
not merely for error in fact or law. The decision could be reviewed
if it was in excess of the visitor's powers, or an abuse of power, or
not made in accordance with natural justice.
Conversely, in R v Disciplinary Committee of the Jockey
Club, ex p Aga Khan,(30) the Court of Appeal declined
to intervene in proceedings at the Jockey Club on the basis that only
private, and not public rights were involved. It is, however, interesting
to note the final words of Lord Justice Hoffmann in that case:
In the present case, however, the
remedies in private law available to the Aga Khan seem to me entirely
adequate. He has a contract with the Jockey Club, both as a registered
owner and by virtue of having entered his horse in the Oaks. The Club
has an implied obligation under the contract to conduct its disciplinary
proceedings fairly. If it has not done so, the Aga Khan can obtain
a declaration that the decision was ineffective (I avoid the slippery
word void) and, if necessary, an injunction to restrain the Jockey
Club from doing anything to implement it. No injustice is therefore
likely to be caused in the present case by the denial of the public
law remedy.
What parallels can be drawn from the law relating to
expert determinations? In his book Expert Determination(31),
John Kendall summarises the position as follows:
Must each side be allowed a
say?
Questions are sometimes raised
about the fairness of procedures adopted by experts. No one would
argue that experts' procedures should not be fair. Difficulties
arise over how to assess whether a procedure is fair, specifically
whether the rules of natural justice apply to expert determinations.
Do the procedures allow each side to have its say and know what
the other side is saying?
Contract law governs the position
The problem arose in an acute
form in the Australian case of Capricorn Inks Pty Ltd v Lawter
International (Australasia) Pty Ltd(32) when the
expert made his decision on the basis of a much larger claim,
unknown to the other party. Commentators have asked(33)
what the effect would be if the parties required their expert
to observe the rules of natural justice. They have argued that
there is no reason why parties should not expect fair procedures
to be followed and that the public law decision Ridge v Baldwin(34)
applies the rules of natural justice to any person making a decision
about individuals. But the dismissal of a chief constable is very
different from a company's claim for damages. Denning LJ (as he
then was) stated(35) that a domestic tribunal must
observe the principles of natural justice but this was in the
context of being given a reasonable opportunity to meet a charge,
in this case the attempt to expel a member from a trade union.
A disciplinary tribunal has been held to be obliged to conduct
its proceedings fairly(36). It would be difficult to
argue against an implied term that an expert will conduct his
determination fairly but fairness does not necessarily bring with
it the whole doctrine of natural justice. It was clearly unfair
in Capricorn Inks(37) for the expert to have
made his decision on the basis of a much larger claim made by
one of the parties without informing the other party but that
does not necessarily oblige the expert never to communicate
with one of the parties without the other knowing which is a requirement
of the rules of natural justice. Further there is no machinery(38)
for the setting aside of experts' decisions for failing to observe
the rulers of natural justice as there is with arbitration awards;
and expert determinations, as decisions made under private contracts,
are not susceptible to judicial review(39) for failing
to comply with the rules of natural justice(40). The
RICS Guidance Notes(41) used to say that the expert
should observe at least the most fundamental of the rules of natural
justice and of evidence. Bernstein & Reynolds(42),
commenting on this, agreed that this was 'good advice for the
expert, but whether a court would criticise one who failed to
heed it remains to be seen. There is much to be said for the view
that by stipulating expert determination the parties have contracted
for a procedure unfettered even by these rules'. The latest edition
of the RICS Guidance Notes has dropped this assertion(43).
The duty does exist, but each
case will need investigation
An expert, therefore, does
have a duty to observe procedural fairness. The matter will be
governed by the terms of reference and the procedure established,
together with any code of conduct adopted. Those arrangements
will have to be interpreted. Difficult cases will arise where
those arrangements do not exist, have not been documented, are
ambiguous or are in conflict with each other.
The Nature of an Adjudicator's Decision
It is generally the duty of an arbitrator to decide
the questions submitted to him according to the legal rights of the
parties, and not according to what he may consider fair and reasonable
under all the circumstances(44). He is thus required to make
a judicial-type of decision. Conversely, an expert is ordinarily entitled
and expected to act according to his own opinion.
The division between the role of the arbitrator and that
of an expert is not absolute. Thus, for example:
- An arbitrator with a power to open up, review and revise certificates
has some of the characteristics of an expert.(45)
- Section 46(1)(b) of the Arbitration Act 1996 allows for arbitrations
to be decided otherwise then in accordance with the law if the parties
so agree.(46)
- The court have sometimes referred to 'look sniff' arbitrations,
in which rather more casual rules apply. Thus, in the first instance
decision in Bremer Vulkan Schiffbau Und Maschinenfabrik v South
India Shipping Corporation Ltd(47) Donaldson J(48)
said:
Arbitrations vary greatly
in their character from major proceedings which are wholly indistinguishable
from a heavy High Court action to disputes on the quality of commodities
(the 'look-sniff' arbitration). But so do actions. Actions prosecuted
under the small claims procedures in the county courts are indistinguishable
from similar claims determined by arbitration under the auspices
of the motor, building or travel industries or by so-called small
claims courts, which are in fact not courts but arbitral bodies.
With the sole exception of the look-sniff arbitration, all employ
the adversary system.(49)
Into which category does an adjudicator fall? There is
no authority on this point, save perhaps that the answer is likely to
depend upon the wording of the adjudication clause rather than on generalised
policy considerations(50). Some guidelines may be tentatively
suggested:
- There may be express provision in the contract or applicable adjudication
rules. For example, the provision at r 15 of the ORSA rules provides
that wherever possible, the decision of the Adjudicator shall reflect
the legal entitlements of the parties, but that where it appears to
the Adjudicator impossible to reach a concluded view upon the legal
entitlements of the parties within the practical constraints of a
rapid and economical adjudication process, his decision shall represent
his fair and commercially reasonable view of how the disputed matter
should lie unless and until resolved by litigation or arbitration.(51)
- If the adjudicator is given power to open up and review certificates
that would be binding on a court, then that suggests that the adjudicator
is not precluded from making a decision according to his own judgment
as to what is fair and reasonable, at any rate for the purposes of
such opening up and review.
- Where the adjudicator is bound to make a decision upon a matter
so complex that it would not be practical to hear or read all the
evidence and submissions within the permitted timescale, then there
may be some ground for concluding that the process cannot be intended
to be in the nature of an arbitration(52). Conversely,
where the adjudicator is permitted or obliged by the contract or adjudication
rules not to make any decision in these circumstances, but to abort
the adjudication, then that would suggest that he is limited to judicial-type
decisions.
- Where the adjudication process is, on a proper analysis, an arbitration,
then the adjudicator is probably limited to judicial-type decisions.(53)
The Orsa Rules
ORSA ADJUDICATION RULES
The Official Referees Solicitors Association
Procedural Rules for Adjudication
1996 Edition v1.1 1. The
following Rules
(i) may be incorporated into any contract
by reference to the "ORSA Adjudication Rules", which expression
shall mean, in relation to any adjudication, the most recent
edition hereof as at the date of the written notice requiring
that adjudication.
(ii) meet the requirements of adjudication
procedure as set out in section 108 of the Housing Grants,
Construction and Regeneration Act 1996; Part I of the Scheme
for Construction Contracts shall thus not apply.
Definitions
2. In these Rules:-
"Contract" means the agreement which includes
the agreement to adjudicate in accordance with these Rules
"Party" means any party to the Contract
"Chairman of ORSA" means the Chairman for the
time being of the Official Referees Solicitors Association,
or such other officer thereof as is
Commencement
3. These Rules shall apply upon any Party giving
written notice to any other Party requiring adjudication, and
identifying in general terms the dispute in respect of which
adjudication is required.
4. Such notice may be given at any time and notwithstanding
that arbitration or litigation has been commenced in respect
of such dispute.
5. More than one such notice may be given arising
out of the same contract.
Appointment
6. Where the Parties have agreed upon the identity
of an adjudicator who confirms his readiness and willingness
to embark upon the Adjudication within 7 days of referral to
him, then that person shall be the Adjudicator.
7. Where the Parties have not so agreed upon
an adjudicator, or where such person has not so confirmed his
willingness to act, then any Party may apply to the Chairman
of ORSA for a nomination. The following procedure shall apply:-
(i) The application shall be in writing,
accompanied by a copy of the Contract or other evidence
of the agreement of the Parties that these Rules should
apply, a copy of the written notice requiring adjudication,
and ORSA's appointment fee of £100.
(ii) The Chairman of ORSA shall endeavour
to secure the appointment of an Adjudicator and the referral
to him of the dispute within 7 days from the notice requiring
adjudication.
(iii) Any person so appointed, and not any
person named in the Contract whose readiness or willingness
is in question, shall be the Adjudicator.
8. The Chairman of ORSA shall have the power
by written notice to the Parties to replace the Adjudicator
with another nominated person if and when it appears necessary
to him to do so. The Chairman of ORSA shall consider whether
to exercise such power if any Party shall represent to him that
the Adjudicator is not acting impartially, or that the Adjudicator
is physically or mentally incapable of conducting the Adjudication,
or that the Adjudicator is failing with necessary dispatch to
proceed with the Adjudication or make his decision. In the event
of a replacement under this Rule, directions and decisions of
the previous Adjudicator shall remain in effect unless reviewed
and replaced by the new Adjudicator, and all timescales shall
be recalculated from the date of the replacement.
9. Where an adjudicator has already been appointed
in relation to another dispute arising out of the Contract,
the Chairman of ORSA may appoint either the same or a different
person as Adjudicator.
Agreement
10. An agreement to adjudicate in accordance
with these Rules shall be treated as an offer made by each of
the Parties to ORSA and to any Adjudicator to abide by these
Rules, which offer may be accepted by conduct by appointing
an Adjudicator or embarking upon the Adjudication respectively.
Scope of the Adjudication
11. The scope of the Adjudication shall be the
matters identified in the notice requiring adjudication, together
with
(i) any further matters which all Parties
agree should be within the scope of the Adjudication, and
(ii) any further matters which the Adjudicator
determines must be included in order that the Adjudication
may be effective and/or meaningful.
12. The Adjudicator may rule upon his own substantive
jurisdiction, and as to the scope of the Adjudication.
The Purpose of the Adjudication and the Role
of the Adjudicator
13. The underlying purpose of the Adjudication
is to resolve disputes between the Parties that are within the
scope of the Adjudication as rapidly and economically as is
reasonably possible.
14. Decisions of the Adjudicator shall be binding
until the dispute is finally determined by legal proceedings,
by arbitration (if the Contract provides for arbitration or
the parties otherwise agree to arbitration) or by agreement.
15. Wherever possible, the decision of the Adjudicator
shall reflect the legal entitlements of the Parties. Where it
appears to the Adjudicator impossible to reach a concluded view
upon the legal entitlements of the Parties within the practical
constraints of a rapid and economical adjudication process,
his decision shall represent his fair and commercially reasonable
view of how the disputed matter should lie unless and until
resolved by litigation or arbitration.
16. The Adjudicator shall have the like power
to open up and review any certificates or other things issued
or made pursuant to the Contract as would an arbitrator appointed
pursuant to the Contract and/or a court.
17. The Adjudicator shall act fairly and impartially,
but shall not be obliged or empowered to act as though he were
an arbitrator.
Conduct of the Adjudication
18. The Adjudicator shall establish the procedure
and timetable for the Adjudication.
19. Without prejudice to the generality of Rule
18, the Adjudicator may if he thinks fit:-
(i) Require the delivery of written statements
of case,
(ii) Require any party to produce a bundle
of key documents, whether helpful or otherwise to that Party's
case, and to draw such inference as may seem proper from
any imbalance in such bundle that may become apparent,
(iii) Require the delivery to him and/or
the other parties of copies of any documents other than
documents that would be privileged from production to a
court,
(iv) Limit the length of any written or oral
submission,
(v) Require the attendance before him for
questioning of any Party or employee or agent of any Party,
(vi) Make site visits,
(vii) Make use of his own specialist knowledge,
(viii) Obtain advice from specialist consultants,
provided that at least one of the Parties so requests or
consents,
(ix) Meet and otherwise communicate with
any Party without the presence of other Parties,
(x) Make directions for the conduct of the
Adjudication orally or in writing,
(xi) Review and revise any of his own previous
directions,
(xii) Conduct the Adjudication inquisitorially,
and take the initiative in ascertaining the facts and the
law,
(xiii) Reach his decision with or without
holding an oral hearing, and with or without having endeavoured
to facilitate an agreement between the Parties.
20. The Adjudicator shall exercise such powers
with a view of fairness and impartiality, giving each Party
a reasonable opportunity, in light of the timetable, of putting
his case and dealing with that of his opponents
21. The Adjudicator may not
(i) Require any advance payment of or security
for his fees
(ii) Receive any written submissions from
one Party that are not also made available to the others
(iii) Refuse any Party the right at any hearing
or meeting to be represented by any representative of that
Party's choosing who is present,
(iv) Act or continue to act in the face of
a conflict of interest
(v) Require any Party to pay or make contribution
to the legal costs of another Party arising in the Adjudication
22. The Adjudicator shall reach a decision within
28 days of referral or such longer period as is agreed by the
Parties after the dispute has been referred to him. The Adjudicator
shall be entitled to extend the said period of 28 days by up
to 14 days with the consent of the Party by whom the dispute
was referred.
Adjudicator's Fees and Expenses
23. If a Party shall request Adjudication, and
it is subsequently established that he is not entitled to do
so, that Party shall be solely responsible for the Adjudicator's
fees and expenses.
24. Save as aforesaid, the Parties shall be jointly
responsible for the Adjudicator's fees and expenses including
those of any specialist consultant appointed under 19(viii).
In his decision, the Adjudicator shall have the discretion to
make directions with regard to those fees and expenses. If no
such directions are made, the Parties shall bear such fees and
expenses in equal shares, and if any Party has paid more than
such equal share, that Party shall be entitled to contribution
from other Parties accordingly.
25. The Adjudicator's fees shall not exceed the
rate of £1000 per day or part day, plus expenses and VAT.
Decisions
26. The Adjudicator may in any decision direct
the payment of such compound or simple interest as may be commercially
reasonable.
27. All decisions shall be in writing, but shall
not include any reasons.
Enforcement
28. Every decision of the Adjudicator shall be
implemented without delay. The Parties shall be entitled to
such reliefs and remedies as are set out in the decision, and
shall be entitled to summary enforcement thereof, regardless
of whether such decision is or is to be the subject of any challenge
or review. No party shall be entitled to raise any right of
set-off, counterclaim or abatement in connection with any enforcement
proceedings.
Immunity, Confidentiality and Non-Compellability
29. Neither ORSA, nor its Chairman, nor deputy,
nor the Adjudicator nor any employee or agent of any of them
shall be liable for anything done or not done in the discharge
or purported discharge of his functions as Adjudicator, whether
in negligence or otherwise, unless the act or omission is in
bad faith.
30. The Adjudication and all matters arising
in the course thereof are and will be kept confidential by the
Parties except insofar as necessary to implement or enforce
any decision of the Adjudicator or as may be required for the
purpose of any subsequent proceedings.
31. In the event that any Party seeks to challenge
or review any decision of the Adjudicator in any subsequent
litigation or arbitration, the Adjudicator shall not be joined
as a party to, nor shall be subpoenaed or otherwise required
to give evidence or provide his notes in such litigation or
arbitration.
|
|
15. (1989) unreported.
16. (1990) 52 BLR 24.
17. (1992) 60 BLR 102, [1992] CILL 768.
18. (1995) 46 Con LR 75.
19. It was variously referred to as 'the disputes
review procedure' or 'review panel procedure'. It seems clear that it
was in the nature of an adjudication provision.
20. Channel Tunnel Group Ltd v Balfour
Beatty Construction Ltd, (1992) 56 BLR 54, [1992] 2 WLR 741, [1992]
2 All ER 609.
21. Channel Tunnel Group Ltd v Balfour
Beatty Construction Ltd [1993] AC 334; [1993] 2 WLR 262; [1993]
1 All ER 664, HL.
22. Save inasmuch as the House of Lords was
plainly anxious that, whatever the legal nature of the procedure agreed
by the parties, the court should so exercise its powers as to support,
and not frustrate, that procedure. The House of Lords said: 'Notwithstanding
that the Court can and should in the right case provide re-enforcement
for the arbitral process by granting interim relief, I am quite satisfied
that this is not such a case, and that to order an injunction here would
be to act contrary both to the general tenure of the Construction Contract
and to the spirit of international arbitration'.
23. Happily, it appears from the statement
made by the Government in the House of Lords on 22 April 1996 that the
Government also agreed.
24. (1996) unreported, CA.
25. It does so by one of the three traditional
prerogative writs of certiorari, mandamus or prohibition.
26. [1949] 1 All ER 109, [1949] 65 TLR 225,
[1949] 93 SJ 132.
27. [1971] AC 297, [1969] 3 WLR 706, [1969]
3 All ER 275.
28. [1993] 3 WLR 1112, HL, [1993] 1 All ER
97, (1993) 137 SJ (LB) 45.
29. The House of Lords summarised the position
thus: 'It is established that, a university being an eleemosynary charitable
foundation, the visitor of the university has exclusive jurisdiction
to decide disputes arising under the domestic law of the university.
This is because the founder of such a body is entitled to reserve to
himself or to a visitor who he appoints the exclusive right to adjudicate
on the domestic laws which the founder has established for the regulation
of his bounty'.
30. [1993] 1 WLR 909, [1993] 2 All ER 207.
31. Second Edition, FT Law & Tax, at section
16.9.
32. [1989] 1 Qd R 8: see 15.13.2
33. Burke and Chinkin in [1989] ICLR 401
34. [1964] AC 40
35. In Lee v Showmen's Guild of Great Britain
[1952] 2 QB 329 at 342
36. R v Disciplinary Committee of the Jockey
Club, ex p Aga Khan [1993] 2 All ER 853 at 876: obiter by Hoffman
LJ (as he then was).
37. Cited above.
38. For arbitration awards it is provided
by Arbitration Act 1996, s 68
39. Under RSC, Ord 53.
40. Jockey Club case cited above.
41. Guidance notes for Surveyors acting as
Arbitrators or as Independent Experts in Rent Review, 6th edn (RICS
Books).
42. 11-52
43. The RICS' Code of practice for commercial
property leases in England and Wales issued in December 1995 states
that an expert 'must act with due care and diligence but is not bound
by the rules of natural justice'.
44. David Taylor and Son Ltd v Barnett
Trading Co [1953] 1 WLR 562 at 568.
45. In Northern Regional Health Authority
v Derek Crouch Construction Co Ltd [1984] 2 WLR 676 [1984] 26 BLR
2, [1984] 2 All ER 175, the Court of Appeal said 'The powers conferred
on the arbitrator are of a different kind. Under clause 35(3) he has
power not merely to determine disputes on legal rights under the earlier
provisions of the contract (including the consequences flowing from
certificates or opinions of the architect). In addition, he is given
power to modify those contractual rights by varying the architect's
certificates and opinions if he disagrees with them by substituting
his own discretion for that of the architect. The arbitrator has power
not only to enforce the contractual obligations but to modify them'.
46. Section 46(1) provides that 'The arbitral
tribunal shall decide the dispute (a) in accordance with the law chosen
by the parties as applicable to the substance of the dispute, or (b)
if the parties so agree, in accordance with such other considerations
as are agreed by them or determined by the tribunal'. But note the special
commencement date for this section.
47. [1979] 3 WLR 471, [1979] 3 All ER 194,
(1979) 123 SJ 504.
48. As he then was.
49. This passage appears to have received
the approval of the Court of Appeal when the matter went on appeal:
[1980] 2 WLR 905.
50. Conoco v Phillips Petroleum (1996)
CILL 1204.
51. There is something of a parallel to this
approach in the case of interlocutory injunctions, where the courts
have for many years adopted the test set out in American Cyanamid
v Ethicon Ltd [1975] 1 All ER 504 [1975] 2 WLR 316, [1975] 119 SJ
136. In that case, the House of Lords said:
52. It is no part of the court's
function at this stage of the litigation to try to resolve conflicts
of evidence on affidavit as to facts on which the claims of either party
may ultimately depend nor to decide difficult questions of law which
call for detailed argument and mature considerations. These are matters
to be dealt with at the trial. One of the reasons for the introduction
of the practice of requiring an undertaking as to damages upon the grant
of an interlocutory injunction was that 'it aided the court in doing
that which was its great object, viz. abstaining from expressing any
opinion upon the merits of the case until the hearing': Wakefield
v Duke of Buccleugh (1865) 12 LT 628, 629. So unless the material
available to the court at the hearing of the application for an interlocutory
injunction fails to disclose that the plaintiff has any real prospect
of succeeding in his claim for a permanent injunction at the trial,
the court should go on to consider whether the balance of convenience
lies in favour of granting or refusing the interlocutory relief that
is sought.
53. As to that, the governing
principle is that the court should first consider whether, if the plaintiff
were to succeed at the trial in establishing his right to a permanent
injunction, he would be adequately compensated by an award of damages
for the loss he would have sustained as a result of the defendant's
continuing to do what was sought to be enjoined between the time of
the application and the time of the trial. If damages in the measure
recoverable at common law would be adequate remedy and the defendant
would be in a financial position to pay them, no interlocutory injunction
should normally be granted, however strong the plaintiff's claim appeared
to be at that stage. If, on the other hand, damages would not provide
an adequate remedy for the plaintiff in the event of his succeeding
at the trial, the court should then consider whether, on the contrary
hypothesis that the defendant were to succeed at the trial in establishing
his right to do that which was sought to be enjoined, he would be adequately
compensated under the plaintiff' undertaking as to damages for the loss
he would have sustained by being prevented from doing so between the
time of the application and the time of the trial. If damages in the
measure recoverable under such an undertaking would be an adequate remedy
and the plaintiff would be in a financial position to pay them, there
would be no reason upon this ground to refuse an interlocutory injunction.
54. Although both court proceedings and arbitrations
are sometimes constrained by guillotines, so that that the mere presence
of a time limit for the proceedings cannot of itself be conclusive.
55. Although it would still remain arguable
that the process is in the nature of a 'look sniff'. |